About Us

We work collaboratively with our clients to build strong, sustainable relationships. Our team is committed to delivering consistent high standards of service, and we understand the importance of accessibility. Working with us, you'll enjoy open communication, meaning well scoped, properly resourced and effectively managed matters.

Learn More

Latest Case

Providing innovative procurement solutions for local government projects April 20, 2018

We advised City of Casey on the procurement process of the Bunjil Place Project. Bunjil Place is a $125 million civic and cultural precinct for the City of Casey, encompassing an 800-seat theatre and 200-seat … Continued

Latest News

Maddocks signs on for Luminance AI platform May 24, 2018

Thursday 24 May 2018 Maddocks has adopted an artificial intelligence (AI) platform to assist in streamlining due diligence processes. The firm has signed on to use the market-leading Luminance AI platform to provide due diligence … Continued

Latest Article

Strategic use of regulatory action policies: an example in the context of Freedom of Information May 23, 2018

Regulatory action policies (including strategies and statements issued by regulators) are a useful tool for regulators to signal the importance of a particular regulatory area to the regulated sector and to the public at large. … Continued

Establishing a panel contract? Don’t forget section 186

It is becoming increasingly common for councils to seek to establish panels for the procurement of works, goods and services over a contract term.

These panel arrangements typically involve:

  • the council seeking tenders from potential contractors, suppliers or consultants for engagement on a panel
  • each successful tenderer being required to execute a single contract with the council under which they agree to provide relevant works, goods or services over a particular term (this Contract Term could involve an initial term plus one or more options to extend the panel)
  • the council issuing a works order to a panel member as and when it requires that particular panel member to provide works, goods or services.

Panel arrangements are attractive for many reasons. These include simplifying the procurement process (since the council only goes out to tender once) and potentially offering significant potential for value for money as panel members can be asked to ‘hold’ their rates (potentially subject to CPI adjustment) over the term of the contract.

It is important, however, for councils to be careful to ensure that they establish and use panels in a way that is consistent with both s 186(1) of the Local Government Act 1989 and the council’s own procurement policy.

This is because a panel arrangement that is not established properly may not give rise to a binding contract being formed for the purposes of section 186(1).

Has your council considered establishing a panel? In what circumstances could they be used at your council? Have you taken steps to ensure that s.186 will be complied with in establishing a panel?

 

Author:
Shane Ridley | Consultant
61 3 9258 3519
shane.ridley@maddocks.com.au

It is becoming increasingly common for councils to seek to establish panels for the procurement of works, goods and services over a contract term.

These panel arrangements typically involve:

  • the council seeking tenders from potential contractors, suppliers or consultants for engagement on a panel
  • each successful tenderer being required to execute a single contract with the council under which they agree to provide relevant works, goods or services over a particular term (this Contract Term could involve an initial term plus one or more options to extend the panel)
  • the council issuing a works order to a panel member as and when it requires that particular panel member to provide works, goods or services.

Panel arrangements are attractive for many reasons. These include simplifying the procurement process (since the council only goes out to tender once) and potentially offering significant potential for value for money as panel members can be asked to ‘hold’ their rates (potentially subject to CPI adjustment) over the term of the contract.

It is important, however, for councils to be careful to ensure that they establish and use panels in a way that is consistent with both s 186(1) of the Local Government Act 1989 and the council’s own procurement policy.

This is because a panel arrangement that is not established properly may not give rise to a binding contract being formed for the purposes of section 186(1).