Principles of contract law: insights from recent case law
We look at cases that illustrate the longstanding principles of contract law governing such matters.
A change in the law has implications for how illegal building works are investigated and prosecuted
Section 16(1) of the Building Act 1993 (Act) is central to the regulation of building work in Victoria. It provides that a person must not carry out building work unless they have a valid building permit for that work and the work is carried out in accordance with that building permit, the Act and the Building Regulations.
From 4 July 2016, s 16(1) of the Act has been amended. The changes shift the responsibility for obtaining building permits squarely to ‘building practitioners’ and architects when they are engaged by an owner. This will have implications for how illegal building works are investigated and prosecuted by local councils and the Victorian Building Authority.
The amended s 16(1) is as follows:
16. Offences related to carrying out building work
(1) A person must not carry out building work unless a building permit in relation to the work has been issued and is in force under this Act.
(2) A person must not carry out building work unless the work is carried out in accordance with this Act, the Building Regulations and the building permit issued in relation to that work.
(3) An owner of land must not permit building work to be carried out on that land unless:
(a) a building permit in relation to the work has been issued and is in force under this Act
(b) the work is carried out in accordance with this Act, the Building Regulations and the building permit issued in relation to that work.
(4) A building practitioner or an architect who is engaged to carry out building work must ensure that:
(a) a building permit in relation to the work has been issued and is in force under this Act
(b) the work is carried out in accordance with this Act, the Building Regulations and the building permit issued in relation to that work.
(5) Subsection (3) does not apply to an owner if the owner has engaged a building practitioner or architect to carry out the building work on that land.
(6) Subsections (1), (2), (3) and (4) do not apply if the building work is exempted by or under this Act or the Regulations.
As can be seen, ss 16(3) provides that a land owner is specifically prohibited from permitting building work to be done on their land without a building permit and/or in breach of the Act, the Regulations or the permit. While on the face of it, this provision would enable the owner to be prosecuted if there is work carried out without a permit, regard must be given to ss 16(5) which goes on to provide that ss 16(3) does not apply to an owner if the owner has engaged a building practitioner or architect to carry out the work.
The term ‘building practitioner’ is defined in the Act as a building surveyor, building inspector, quantity surveyor, engineer engaged in the building industry, draftsperson, builder including a domestic builder, person who erects temporary structures or other person who belongs to a class or category of people prescribed to be building practitioners.
The amendments to the wording of s 16 are significant. While s 16(1) has always stated that ‘a person must not carry out building work….’, it was commonly argued that an owner could be liable for the breach, even where they did not physically carry out the work. The reasoning was that the owner was responsible for carrying out the work through their engagement of a builder or tradesmen to undertake the works when no building permit was in place. This reasoning was supported by s 17 of the Act, which provides that it is the owner that applies for the building permit.
However, the new ss 16(5) expressly states that the requirement that the owner obtain the relevant building permit does not apply to an owner if the owner engaged a building practitioner or architect to carry out the building work on that land.
Accordingly, under the amended s 16(1), before enforcement action may be taken, it will be necessary to first find out if the owner engaged a ‘building practitioner’ or architect to carry out the work. If such a person was engaged by the owner then any prosecution proceedings based on breach of s 16 will necessarily need to be commenced against the building practitioner or architect engaged by the owner.
The implications of these amendments are as follows:
While prosecution proceedings against owners with respect to the carrying out of illegal works may now be much more difficult, a municipal building surveyor could still issue an owner with a building notice and/or order in relation to the illegal works. If the owner does not comply with a valid building order, council could issue proceedings against an owner for an offence under s 118 of the Act.
In summary, any ‘building practitioner’ or architect engaged by an owner must now ensure that a building permit is obtained regarding that work or they could be in breach of s 16(4). Further, in investigating illegal work, a council will need to determine whether an owner can get the benefit of s 16(5) before they decide whether to prosecute an owner.
Keep up to date with our legal insights and events
Sign upWe look at cases that illustrate the longstanding principles of contract law governing such matters.
The Government announced this week that it will defer the implementation of formal price caps under Support at Home
This insight outlines the key measures and what they mean for agencies responsible for implementation and governance.
Privacy Awareness Week (PAW) is an opportunity for NSW public sector agencies to reflect on how smart technologies – ...