Victoria's Housing Statement brings bold reforms and an ambitious vision for the decade ahead
The Victorian Government published the Housing Statement in September 2024.
Developers and head contractors operating in Queensland should familiarise themselves with the project bank accounts regime and reforms to security of payment legislation.
The Queensland Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) commenced in November 2017 and introduced reforms to several aspects of security of payment in the construction industry in Queensland, some of which are still being phased in.
This article looks in particular at the phase in of project bank accounts for construction projects which already apply to some Government projects and will apply to private sector construction projects, likely later this year – and also summarises the key changes to the payment process.
The obligations under the project bank accounts regime are required to be performed by head contractors primarily and, to a lesser extent, by principals, while subcontractors are the main beneficiaries. However, the security of payment changes, which came into effect on 17 December 2018, made it easier for claimants to secure payment so all industry participants should consider their internal processes for managing and responding to payment claims when operating in Queensland.
Importantly, penalties may apply for non-compliance with particular provisions of the new and updated regimes.
Phase 1 of the project bank accounts (PBA) regime applies to Government[1] contracts released for tender after 1 March 2018 for ‘building work’[2]:
Phase 2 will expand the scope of PBAs to the private sector to cover most building and construction projects over $1 million, and is expected to commence later in 2019[3].
Where a PBA is required, a head contractor must establish three separate trust accounts within 20 business days after the head contractor enters into the first subcontract for the project (or earlier if specified in the head contract). These are:
Head contractors also have a range of other obligations, including (amongst other things):
Principals must pay funds owing to the head contractor into the general trust account. There are only limited exceptions for not doing so. Payment into the general trust account discharges the principal’s liability to pay under the head contract.
Retention funds are now required to be quarantined, so that upon that party becoming insolvent the retention funds can be allocated to the subcontractor to which the funds should have been paid contractually.
The disputed funds trust account becomes relevant where a payment dispute arises after a subcontractor has given a head contractor a payment claim for a progress payment if:
Where this occurs, the head contractor must transfer the payment claim amount into the disputed funds trust account and immediately inform the subcontractor in writing of the transfer.
Any funds remaining in the disputed funds trust account after the dispute resolution process has been exhausted must be either transferred back to the general funds trust account (if applicable) or withdrawn for payment to the head contractor.
A PBA can only be dissolved when:
The BIF Act[4] provided for the repeal of the Building and Construction Industry Payments Act 2004 (Qld) (BCIPA) and the Subcontractors’ Charges Act 1974 (Qld) (SCA), Qld’s previous key security of payment legislation. To a large extent, the BIF Act replicates the provisions of the BCIPA and the SCA (and joins the provisions into a single Act) – subject to a number of important changes, including:
Developers and head contractors operating in Queensland should familiarise themselves with the PBA regime and reforms to security of payment legislation under the BIF Act, given the risk of a non-compliance may now result in a statutory penalty.
[1] And any statutory authorities that have opted in to the scheme.
[2] The definition of ‘building work’ under the BIF Act includes, amongst other things, the construction, renovation or repair of a building, lighting, HVAC and water supply work, site work, the preparation of plans or specifications for the performance of building work, contract administration, and building inspections. Regulations made under the BIF Act provide that scaffolding work, building certification and energy efficiency assessments are also ‘building work’, but the BIF Act does not apply to any engineering or infrastructure work, such as tunnel, road or rail projects or a residential construction work contract, unless it's for 3 or more living units with the Department of Housing and Public Works as the principal.
[3] The Qld Government has previously stated that the Phase 2 reforms applicable to the private sector would not commence ‘before 1 March 2019’. As at 6 May 2019, Phase 2 has not been rolled out.
[4] Which commenced on 10 November 2017.
Contact the Construction team.
Keep up to date with our legal insights and events
Sign upThe Victorian Government published the Housing Statement in September 2024.
Recent announcement that the Victorian Building Authority (VBA) would be replaced by a new, ‘one stop shop’ regulator.
A look at the Victorian Government's off-the plan stamp duty concession scheme designed to to increase housing supply.